South Coast Institute of Technology IoW - L Block & CECAMM

Key Facts - L Block Refurbishment

Heading #1
Start on site
August 2023
Completion date
November 2023
New Build Area (m²)
104m²
Total Project Budget
£302,500
Funder
DfE Institutes of Technology
Architects, Lead Designers, Principal Designers
Saunders Architects
Structural Engineer
N/A
Services Consultant
Ion Consulting
Cost Consultants
FBR
Project Manager, Employer’s Agent, Bid Writers
PMc
Main Contractor
Scape Construct Ltd

Key Facts - CECAMM Extension

Heading #1
Start on site
November 2023
Completion date
July 2024
New Build Area (m²)
215m²
Total Project Budget
£1.1m
Funder
DfE T-Levels
Architects, Lead Designers, Principal Designers
Saunders Architects
Structural Engineer
Scott White & Hookins
Services Consultant
Ion Consulting
Cost Consultants
FBR
Project Manager, Employer’s Agent, Bid Writers
PMc
Main Contractor
TBC

Project Team

Current Plans - CECAMM

Current Plans - L Block