South Coast Institute of Technology IoW - L Block & CECAMM Key Facts - L Block Refurbishment Heading #1 Start on siteAugust 2023Completion dateNovember 2023New Build Area (m²)104m²Total Project Budget£302,500FunderDfE Institutes of TechnologyArchitects, Lead Designers, Principal DesignersSaunders ArchitectsStructural EngineerN/AServices ConsultantIon ConsultingCost ConsultantsFBRProject Manager, Employer’s Agent, Bid Writers PMcMain ContractorScape Construct Ltd Key Facts - CECAMM Extension Heading #1 Start on siteNovember 2023Completion dateJuly 2024New Build Area (m²)215m²Total Project Budget£1.1mFunderDfE T-LevelsArchitects, Lead Designers, Principal DesignersSaunders ArchitectsStructural EngineerScott White & HookinsServices ConsultantIon ConsultingCost ConsultantsFBRProject Manager, Employer’s Agent, Bid Writers PMcMain ContractorTBC Project Team Current Plans - CECAMM Current Plans - L Block