The Loddon School – Forest Oak (Phase 1)

The Loddon School - Phase 1

Introduction

The Loddon School is an independent residential school, providing year-round education and care for children who have complex learning difficulties and who can no longer live at home due to their exceptional support needs. 

The school estate comprises a mix of  buildings developed over time between the 1860s and 1930s, with more recent purpose-built buildings; providing homes, education, leisure, play, outings and holidays for some 28 children and staff members.

The Loddon School is rated Ofsted ‘Outstanding’ and the delivery of new purpose-built homes for its students is a core part of its strategy to provide the very best environment for both learning and care for the young people it serves.

Overview

PMc was appointed to develop an Estates Strategy in the Spring of 2018, this was completed and approved by the Board of Trustees in September 2018.  The Strategy provides a long-term estates route map to meet the school’s strategic estate needs and bring all of the school’s pupil-focused accommodation onto the main site and out of the Main House into purpose-built homes. Following the adoption of the Strategy, the Loddon School is proceeding in 2019/20 with the delivery of the first phase of a three-phase project. 

Phase 1 involves the construction of the ‘Forest Oak’ houses, which comprise two, 260 m2 single-storey houses, with associated external works to provide living, learning and sleeping accommodation for up to 12 children. PMc are acting as the Client’s Representative, Project Manager, Employer’s Agent and Quantity Surveyor on this project alongside the retained design team led by APLB architects.

Key Facts

Heading #1
Start on site
September 2023
Completion date
August 2025
New Build Area (m²)
650m²
Total Project Budget
£1.9m
Funder
DfE FECTF & Land Disposal
Architects
Rock Townsend
Cost Consultants
G&T
Project Manager, Employer’s Agent, Bid Writers
PMc
Main Contractor
TBC

The Projects Objectives are: 

  • Develop an Estates Strategy to provide a long-term map of the schools’ estate needs.
  • Construction & Development of two single-storey residences to accommodate the needs of 12 students as part of phase one delivery.
  • Delivery of the subsequent two phases of development including the creation of a new two-storey building to accommodate the younger learners at the School.

 

Project Team

Media

The Loddon School – Maple Grove (Phase 2)

The Loddon School Maple Grove - Phase 2

Key Facts

Heading #1
Start on site
September 2023
Completion date
January 2025
New Build Area (m²)
710m²
Total Project Budget
£3,952,000
Funder
The Loddon School
Architects
Re-Format
Other Designers
White & Lloyd, Lanmor Consulting, UBU Design
Technical Advisors
TBC
Cost Consultants
PMc
Project Manager, Employer’s Agent & Bid Writers
PMC
Main Contractor
DM Habens

Project Team

Buckinghamshire College Group – High Wycombe New Build

Buckinghamshire College Group - High Wycombe New Build

Introduction & Overview

Following the creation of Buckinghamshire College Group, PMc worked with the Group to complete a detailed analysis of a number of strategic options for the location of their provision in the South of the County and the subsequent development of an outline business case. We concluded that a new consolidated, purpose-built single provision for the South of the County to be the optimal solution which would enable the Group to grow its further and higher education offering and provide a learning environment that reflects the needs of businesses in the local economy. After an extensive process, PMc supported the Group through the site evaluation process from which a final site was selected in High Wycombe, comprising two land parcels on Oxford Road and Brook Street.  

PMc also supported the Group through the land sale process of two existing sites and helped them obtain an off-market disposal to a local developer.To allow the project to fully funded we also wrote and submitted a Further Education Capital Transformation Fund bid on behalf of the College in which we helped secure over £21m of funding.  

PMc are acting as Strategic Advisor and Project Manager from which we have helped the Group develop the proposals from the initial brief, through the planning process and to the point of appointing a contractor and commencing works on site. The project is due to complete in Summer 2027 ready to open for the 2027 academic year.  

PMc have also continued to support the Group through their ongoing estate improvement works across their existing College estate, including: 

  • Business, Admin, Legal, Law, Hair and Beauty  
  • Health, Science, Early Years and Digital 
  • Construction 
  • Plumbing workshops 

We have supported the College through the land sale process of the two existing sites which we achieved an off-market disposal to a local developer. Through the contract negotiations, we also secured staged payments with vacant possession being provided once the new College site is complete. 

To allow the project to fully funded we also wrote and submitted a Further Education Capital Transformation Fund bid on behalf of the College in which we secured over £19m of funding.  

Working along side Rock Townsend (architects) and the wider design team, the proposals were developed to RIBA Stage 3a with planning submitted in early summer 2023 and a resolution to grant permission was agreed in January 2023. During the planning process the design team developed the designs to RIBA Stage 3b. In the Spring and Summer of 2023 we completed further value engineering design work to align costs and budget and procured a demolition contractor to remove existing buildings on site prior to a main contractor being appointed later in 2023 to complete the building works. 

Key Facts

Heading #1
Start on site
September 2025
Completion date
Summer 2027
New Build Area (m²)
8,472m²
Total Project Budget
N/A
Funder
DfE
Architects
Bond Bryan Architects
Technical Advisors
Rock Townsend
Project Manager, Employer’s Agent, Bid Writers
PMc
Cost Consultants
G&T
Main Contractor
Kier

Project Team

Design Access Statements

Design Accsess Statement: Part 1
Design Accsess Statement: Part 2

Buckinghamshire College Group – T Levels

Buckinghamshire College Group - T Levels

Key Facts

Heading #1
T Level
Wave 2 – Health, Science, Early Years and Digital
Wave 3 – Construction ​
Wave 4 – Business, Admin, Legal, Law, Hair and Beauty ​
Start on site
June 2021
August 2021
May 2023
Completion date
August 2021
October 2022
August 2023
New Build/Refurbishment Area (m²)
960m²
206m²
656m²
Total Project Budget
£765,000
£634,000
£685,000
Funder
DfE T Levels
DfE T Levels
DfE T Levels
Architects
PMc
Bond Bryant
Rock Townsend
Cost Consultants
PMc
PMc
PMc
Project Manager, Employer’s Agent, Bid Writers
PMc
PMc
PMc
Main Contractor
Willmott Dixon Interiors
Ellis Construction
Axis House

T Level Wave 2 - Health, Science, Early Years and Digital

T Level Wave 3 - Construction

T Level Wave 4 - Business, Admin, Legal, Law, Hair and Beauty

South Staffordshire College – Tamworth New Build

South Staffordshire College - Tamworth New Build

Introduction & Overview

South Staffordshire College was formed as part of a merger between Cannock Chase Technical College, Rodbaston College and Tamworth and Lichfield College in 2009.The College’s estate comprises three freehold sites in Cannock, Tamworth and Rodbaston, shared use of a site in Lichfield and a smaller site leased from the County Council in Tamworth known as TORC. The Tamworth and TORC site total 15,327m2 of space comprising a number of buildings, sports grounds and car parking.

PMc were approached by South Staffordshire College in 2019 to develop an estate strategy for their four College’s campuses Lichfield, Rodbaston, Cannock & Tamworth. This consisted of completing detailed reviews of the estates and developing a medium to long term master plan for the College Estate. Our estate assessment and space planning work established that the College had a substantial excess of space within their Tamworth campus. At the point of completing the strategy we developed a phasing plan for the consolidation and rationalisation of the estate on that campus, on the basis that a new-build option could only be delivered with substantial capital support from the Council or another third party.

Tamworth Borough Council subsequently developed plans to regenerate the town centre of Tamworth with the potential support of the Future High Streets Fund (FHSF) which is a funding initiative from the Ministry of Housing, Communities & Local Government to provide financial support to town centres adapting them to the needs of the future. PMc worked with the College, the Council and their consultant team to produce the successful FHSF funding bid which has secured £30m+ for investment in the Town Centre. As part of this bid we ran a Design Approach Competition in partnership with the Local Authority and chose Ayre Chamberlain Gaunt architects as the lead designer.

PMc have played a major part in obtaining a further £14m of FECTF grant funding towards the £30m project for the college along with £6m in site sales receipts from Homes England via the forward sale of the current land. Peter presented the scheme to the Planning Authority in October 2022 and led the College, with its lawyers, through the complex process of agreeing site sale and lease contracts, the JCT D&B contract, sale agreement to Homes England, long lease from the Council for the new site and Section 106 and road diversion
agreements.

The project commenced onsite in spring 2023. The PMc team continues to support the College through to project completion in Summer 2025 acting as strategic client advisors and the specification of FFE requirements and stakeholder liaison through the RIBA Stage 4 & 5 design process.

Key Facts

Heading #1
Start on Site
June 2024
Target Completion Date
August 2025
New Build Area (m²)
6,950m²
Total Project Budget
£30m
Funders
Department of Education, Future Highstreet Fund, South Staffordshire College
Architects
Ayre Chamberlain Gaunt
Client Advisor
PMc
Bid Writer
PMc
Cost Consultants
Pic
Project Manager
McBains
Main Contractor
Kier Construction

Project Team

Isle of Wight College – T Levels

Isle of Wight College - T Levels

Introduction

The Isle of Wight College is an FE college of 28,296m2, located centrally on the island in the principal town of Newport. The College operates from two campuses known as the main campus and the CECAMM (Centre of Excellence for Composites, Advanced Manufacturing and Marine) campus. There has been significant investment in new buildings over the last 12 years, including most recently the creation of CECAMM, P Block, S Block and the Pathways buildings completed in 2017. Since 2022 PMc has been supporting the college in the submission of bids to the Department for Education (DfE) to support the delivery of T Levels across a number of sector areas. We have also supported the feasibility, design, Project and Cost Management, and client fit-out for these Projects.

Key Facts

Heading #1
T Level
Wave 3 – Childcare
Wave 3 – Digital
Wave 3 – Business & Admin
Wave 3 – Healthcare
Wave 3 – Engineering
Wave 4 – Construction – Plumbing
Wave 5 – Hair & Beauty
Wave 5 – Design & Creative
Start on site
May 2022
May 2022
May 2022
May 2022
May 2022
October 2023
September 2023
April 2024
Completion date
August 2022
August 2022
August 2022
August 2022
August 2022
February 2024
January 2024
August 2024
New Build/Refurbishment Area (m²)
455m²
340m²
365m²
385m²
272m²
720m²
350m²
230m²
Total Project Budget
£520,000
£570,000
£390,000
£420,000
£320,000
£1.25M
£650,000
£650,000
Funder
DfE – T Levels
DfE – T Levels
DfE – T Levels
DfE – T Levels
DfE – T Levels
DfE – T Levels
DfE – T Levels
DfE – T Levels
Architects
PMc
PMc
PMc
PMc
PMc
Saunders Architects
PMc
PMc
Services Engineers/Technical Advisors
N/A
N/A
N/A
N/A
N/A
Pentrevion, Parrish Consultancy, Scott White and Hookins
Parrish Consultancy
Parrish Consultancy, Our MEP
Cost Consultants
PMc
PMc
PMc
PMc
PMc
Ridge & Partners
PMc
PMc
Project Manager, Employer’s Agent, Bid Writers
PMc
PMc
PMc
PMc
PMc
PMc
PMc
PMc
Main Contractor
Scape Construct Ltd
Scape Construct Ltd
Scape Construct Ltd
Scape Construct Ltd
Scape Construct Ltd
Scape Construct Ltd
Scape Construct Ltd
SM5 Developments

Testimonials

The new Business Centre, opening June 2022, was created out of a dormant, and poorly used, space in one of our blocks (L).  The space was open plan and had not been used effectively in any number of configurations. 

With Peter Marsh Consulting, and their Project Managers, a plan was established to isolate this space into two rooms that would be presented in a style similar to the highest quality conference facilities expected in some of our major city Hotels.  The design brief was essentially about creating space that challenged the expectations of accommodation traditionally found in a school/college environment, and would be different in every form.

The use of full glass walls on three sides of this new room, with an additional breakout small meeting room (with excellent views of the College campus and beyond), has most certainly achieved that objective.  Effective selection of furniture allows for the formatting of the main room to be anything from traditional conference to small group work.  High quality audio-visual hardware ensures that delegates can engage fully in current teleconferencing and to the highest of standard.  

The projects management was excellent with a great stress on client engagement and participation throughout.  The project managers were very adaptive to the needs and interests of the College with the result that the outcome has exceeded expectations.  Given that the objective was to provide an environment within the College that employers would feel represented them, and the standards they may expect when attending significant national and international conferences, the completed facility more than achieves that.  Supplementary works to the local environment around it have also helped ensure the uniqueness of the accommodation within the College.    

Our summary review is that anyone attending the new Centre will be amazed and surprised that such high quality accommodation is available on the Island, and that it is bespoke to their needs as employers and members of the community. 

T Level Wave 3 - Childcare

T Level Wave 3 - Digital

T Level Wave 3 - Business Centre and Admin

T Level Wave 3 - Healthcare

T Level Wave 3 - Engineering

T Level Wave 4 - Construction - Plumbing

T Level Wave 5 - Hair & Beauty P Block

Isle of Wight – Q Block Pathways – Copy

Isle of Wight - Creative & Digital

Introduction & Overview

Key Facts

Heading #1
Start on site
15th July 2024
Completion date
16th September 2024
Project Area (m²)
230m²
Total Project Budget
£450,000
Funder
DfE
Architects
PMc
Client Advisors
PMc
Cost Consultants
PMc
Project Manager
PMc
Main Contractor
SM5 Developments

Project Team

Isle of Wight – Q Block Pathways

Isle of Wight - Q Block pathways

Introduction & Overview

The Isle of Wight College approached PMc in Summer 2024 to manage and oversee the refurbishment of a portion of the Ground Floor of their Q Block, which consists of the college facilities for teaching SEND students. The project brief was to refurbish a condemned hydrotherapy room, which had issues since the building opened in 2015, into a newer, larger sensory room. In addition, the rooms adjacent were refurbished to help support the new sensory room to provide a sensory deprivation room, a salon/wellbeing room, a de-escalation room, and storage.
 
Due to time restrictions to deliver the project, PMc provided Stage 2 designs and managed the 2-Stage tender process, where SM5 Developments were appointed under a PCSA, and ultimately under a JCT MWD 2024 contract. PMc oversaw the coordination of designs from RIBA Stage 2 to RIBA Stage 4. The works began on site in October 2024 and the project was completed before Christmas 2024, on time and within budget.

Key Facts

Heading #1
Start on site
October 2024
Completion date
December 2024
Project Area (m²)
128m²
Total Project Budget
£345,000
Funder
DfE
Architects, Lead Designers, Principal Designers
PMc, Boyle & Summers
Services Designers
OurMEP
Client Advisors
PMc
Cost Consultants
PMc
Project Manager, Employer’s Agent, Bid Writers
PMc
Main Contractor
SM5 Developments

Project Team

Isle of Wight South Coast Institute of Technology – L Block & CECAMM

South Coast Institute of Technology IoW - L Block & CECAMM

Key Facts - L Block Refurbishment

Heading #1
Start on site
August 2023
Completion date
November 2023
New Build Area (m²)
104m²
Total Project Budget
£302,500
Funder
DfE Institutes of Technology
Architects, Lead Designers, Principal Designers
Saunders Architects
Structural Engineer
N/A
Services Consultant
Ion Consulting
Cost Consultants
FBR
Project Manager, Employer’s Agent, Bid Writers
PMc
Main Contractor
Scape Construct Ltd

Key Facts - CECAMM Extension

Heading #1
Start on site
November 2023
Completion date
July 2024
New Build Area (m²)
215m²
Total Project Budget
£1.8m
Funder
DfE T-Levels
Architects, Lead Designers, Principal Designers
Saunders Architects
Structural Engineer
Scott White & Hookins
Services Consultant
Ion Consulting
Cost Consultants
FBR
Project Manager, Employer’s Agent, Bid Writers
PMc
Main Contractor
TBC

Project Team

Current Plans - CECAMM

Current Plans - L Block

Isle of Wight College CECAMM – Project Assurance

Isle of Wight CECAMM - Project Assurance

Introduction & Overview

In 2014, the Isle of Wight College secured approval to a £11 million bid to develop a new 3,000m2 Centre of Excellence for Composites, Marine and Advanced Manufacturing from the Solent LEP, as part of its investment commitment to the future skills needs of the Solent economy. The facility will be located in Whippingham, East Cowes, offering specialised education and training for around 600 students. The bid for funding for this project was led by GKN Aerospace and supported by other local employers in the composites, marine and advanced manufacturing industries

Our Role

PMc Ltd were appointed by the Solent LEP to provide project assurance and advice to the College and the LEP on the delivery of the new Centre of Excellence for Composite, Advanced Manufacturing and Marine. We worked with the College, their contractor and the project manager to close a £2m gap in the project budget and were delighted that contracts were entered into in December 2015 – on budget and in scope. The Contract with construction partners, Balfour Beatty, was let in December 2015 and the new Centre opened to learners in September 2017.  Throughout the construction period PMc supported the College and the Solent LEP in the delivery of this important project – bringing our skills, knowledge, and experience to help create an outstanding new learning environment on the Isle of Wight.

Testimonials

Testimonials

“Peter Marsh was appointed by the Solent LEP to help the Isle of Wight College and its professional team address a £2m difference between the available funds and the post tender cost packages on the College’s flagship ‘Centre of Excellence for Composites, Advanced Manufacturing and Marine’. His first priority was to clearly understand the College’s strategic priorities for this project and how it would benefit the students and employers. Peter’s comprehensive experience enabled him to quickly identify a broad range of solutions and devise a robust and structured framework for addressing the identified gap which built on the Value Engineering process that the College had commenced. With clear targets set and a timetable for action agreed, the College and their advisors were able to bring the project back within budget whilst preserving the required level of contingency to offset identified risks.  Peter’s no-nonsense approach and significant experience of working with LEPs and contractors on other projects helped us secure the funding for the project and maintain the confidence of the LEP in our combined ability to deliver.”

Debbie Lavin, Principal (to 2022), Isle of Wight College

“The Solent LEP is committed to an ambitious programme of investment to support economic growth and raise productivity levels in the Solent. Developing the areas pipeline of marine engineering skills forms an important part of our investment programme, and the Isle of Wight’s Centre of Excellence for Composite, Advanced Manufacturing and Marine is a key project for the LEP.  The LEP approached Peter Marsh Consulting to assist the College with delivery of the project.  Peter has worked effectively with the College, their advisors and the LEP’s due diligence consultant to ensure the project has a solid basis for delivery.”

Stuart Baker, Head of Local Growth, Solent LEP